Project Management for Construction - Assignment Example

Extract of sample
Project Management for Construction

6) The total amount certified for payment to the contractor by the client/employer is 6,750,000
7) The retention percentage is 10% prior to practical completion (for the main contract)
8) The amount received from the client to date is 5,850,000
9) The total amount certified for payment to package contractors is 5,800,000
10) The total value of package contracts let is 7,500,000
11) There are no retentions held against package contractors-however the current amounts certified but outstanding (i.e. unpaid) to them is 300,000
12) The cladding package contractor to whom the contractor owes 100,000 (including in the 300,000 above) has just become insolvent. The cladding is complete but no warranties have yet been received
13) The current certified installment is one month overdue for payment from the client/employer whose shares have halved in value during the last year
14) We have no other contracts with this client/employer
15) There has been exceptionally inclement weather for the last three months
16) The contract is currently expected to be completed three weeks late
17) Liquidated and ascertained damages are set at 30,000 per week
18) Claims by package contractors currently stand at 200,000
19) Counter-claims package contractors currently stand at 75,000
20) There was an accident on site last month in which a package contractor's employee lost a leg. The Health and Safety Executive are currently investigating this accident.
21) In the last month there has been a two week strike by the Professional League of Plumber (PLoP) which affected the Mechanical, Electrical and plumbing package contractor on the site
22) We calculate that the value of uncertified work carried out is 300,000 of which...
These factors would relate to profits of the project, company mission and objectives, the financial issues in the company, the contractual obligations, commercial aspects and marketing procedures, and also the raw materials used by the contractor. Recommendations are provided on how the contractor should control its commercial department and what are the points that should be emphasized to report on the financial status of the company.
This report is on the examination of the contract No. 205 for construction of offices and yards for Russ Ting metal Stockholders plc. The report will consider the factors that have to be taken into account for determining the current financial and commercial status of the project. In this report I would consider how these factors will affect the financial status of the project. For this all the financial elements are considered in accordance with the following points.
23) The architect's drawing (correctly) showed doors of width 920mm but the ...Show more

Summary

I have just been asked by the Commercial Department of the Contractor for whom I work to examine contract No 205 (for the construction of offices and yards for Russ Ting metal Stockholders plc) and report on its financial status.
Writing a report for my employers setting out the factors that need to be taken into account in determining its current financial/commercial status - The report includes a table setting out how the determination of different factors will affect the financial status of the project…
Author : hazle52
Project Management for Construction essay example
Read Text Preview
Save Your Time for More Important Things
Let us write or edit the assignment on your topic
"Project Management for Construction"
with a personal 20% discount.
Grab the best paper

Related Essays

Project management
Because of the increasing tourism in the UAE, Palm Jumeirah is developed in such a way that the project serves to the tourism industry as well as the natural beauty of the country. The greatest benefit that the island served was to be the project that bought international recognition and fame to the small country.
7 pages (1750 words) Assignment
Project management
It then discusses possible approaches to procurement, identifying and justifying a procurement strategy for the different phases of the project lifecycle, including consultant appointment processes and contract types. Finally, a detailed schedule for the duration of the project will be provided that is fit for the purpose of managing the pilot project.
18 pages (4500 words) Assignment
Strategic Management in the quality of construction
These effective strategic plans would enable the business to be able to gain competitive advantage and future growth chances. In the same way the strategic management is necessary in the construction and the quality of construction which is supposed to enhance the work carried out in the rapidly changing environment.
8 pages (2000 words) Assignment
BIM and Construction management
This modeling came into existence in late 20th century particularly the 70s, and it remained recognized only among few engineers until 1987 when it was recognized fully and developed as a program in ArchiCad developed by Graphisoft. BIM is concerned with adoption of new and advanced technology in the construction industry; and emphasizes on information; communication of information across all sectors of the construction work; use of digital options for transforming physical facilities or buildings and sharing of this information for decision making.
4 pages (1000 words) Assignment
Project Management for Construction Assignment
205. as per the directions of the commercial department, I have been in the process of undertaking an assessment of the project and its progress from all possible financial aspects and have made a number of observations with regards to the financial status of the project.
6 pages (1500 words) Assignment
The project management in the construction and operation of a restaurant
in order to sustain in the market. Project management helps the organization in this regard to find out the solution for these problems in a scientific manner. The timely finish of successful projects requires an understanding of both the technical and human resource components of project management.
19 pages (4750 words) Assignment
Project Management: The Grove Student Retreat Centre
The researcher analyzes his duties as Project Manager and leader of the project team as to make an appeal to everyone for support, understanding and full cooperation towards our new colleagues, provide them with support and intervention, whenever needed and I initiate full-day training sessions on leadership and communication skills.
12 pages (3000 words) Assignment
Construction management
The first thing that I noticed was that the target for the worker force was tight and very unrealistic. For example, we expect that the project be through by the end of two months, which a short duration was
3 pages (750 words) Assignment
BIM and Construction management
ce in late 20th century particularly the 70s, and it remained recognized only among few engineers until 1987 when it was recognized fully and developed as a program in ArchiCad developed by Graphisoft. BIM is concerned with adoption of new and advanced technology in the
4 pages (1000 words) Assignment
Construction management
Accordingly, the following sections will help to define the way this risk analysis has been performed, how these risks are ranked, and the steps and considerations that it been taken as a function of seeking to ameliorate them within the scope of the project
11 pages (2750 words) Assignment
Get a custom paper written
by a pro under your requirements!
Win a special DISCOUNT!
Put in your e-mail and click the button with your lucky finger
Your email
YOUR PRIZE:
Apply my DISCOUNT
Comments (0)
Rate this paper:
Thank you! Your comment has been sent and will be posted after moderation