Contracts Coursework example
High school
Coursework
Engineering and Construction
Pages 12 (3012 words)
Download 0
Contracts Coursework 10/20/2012 Executive Summary The recommendation described below reflects the assessment of this author based on the provisions indicated by the NEC3-ECC contract frame work. I shall describe an alternative framework that may provide more understanding and coverage as far as ensuring project completion…

Introduction

The consultant’s documents were submitted on time, planning permissions gained and quotes received from various contractors. The project was awarded under NEC3-ECC conditions of contract. The Project duration was agreed to be 26 months and payment to the contractor through interim valuations. The project was delayed due to late payment, lack of workmen on site, work behind schedule and late project administrator’s instructions. The contention between the parties was about payment, contractual standing of contractor’s program and principle guiding claim and dispute resolution. The project ran into great difficulties after the 10th month, accusation were exchanged, agreed payments not made and the workmen were pulled off site by the contractor which led to dispute. Table of Contents Executive Summary 1 Table of Contents 2 Introduction 3 General Principle of Construction contracts 4 Dispute resolution guidelines 5 Comparable Analysis of NEC3-ECC, JCTO5 SBC/Q 6 NEC3-ECC 8 JCTO5 SBC/Q 9 Clear Difference 10 Recommended Approach 11 References/Bibliography 14 Introduction AOS Development is a national housing development company in Edinburgh and has embarked on eighty housing units developments in Skye, Scotland. The consultant’s documents were submitted on time, planning permissions gained and quotes received from various contractors. ...
Download paper
Not exactly what you need?

Related papers

controlling your building business
Company Structure •BOD consists of five members. •The chairman will also act as the chairman of all other companies in their group. •Vice chairman will also be the real C.E.O of the firm. •GM department. •F.A department where accounting, treasury and finance participated. •HR Department. •Organisational Department. •Information communication and technology department where…
Re-negotiations in PPP Transport Infrastructure Projects
Majority of these engagements are made effective via a group of diverse companies and contractual concessions. According to Smith (2002) the Principal refers to the one responsible for granting a concession and the ultimate owner of the facility after transfer. They are mostly government agencies, or regulate monopolies. On the other hand, the promoter is the organization that is granted the…
Design-build and Design-Bid-Build Contracts: Their Advantages and Disadvantages
The design-build and design-bid-build are the two forms of contracting in this regard that are most commonly considered while planning for a construction project. While the design-build is a traditional method, the other is an alternative form of contracting involving greater complicacies. Also, these two systems have their respective advantages and disadvantages that can significantly affect the…
NEC3
As a contract administrator you have been tasked to produce a report explaining how the NEC3 Contract works and how it differs from the JCT2011 Contracts highlighting the possible implications for administering a project with the NEC3. Introduction New Engineering Contracts 3rd Edition or NEC3 is a modernistic family of contracts of contracts. It helps in implementing construction project…
NEC ECC Contracts
General Construction. Contract Principles The Housing Grants, Reconstruction and Regeneration Act 1996 (HGRRA) focuses on payments under a construction contract. Specifically, the Act states that, when a construction contract is for 45 days or more that the party to the construction contract is entitled to installment payments (HGRRA 1996 §109). Section 111 of the HGRRA 1996 states that a…
Procurement & Contracts Coursework
57). One of the key attributes of PPP is that it not only facilitates public-private partnerships during the construction phase, but it provides for post-construction services to be managed by a private agency. It has been argued that by taking this approach, the construction design is usually conducted contemplating subsequent services which ultimately lowers the cost of services. Moreover, the…
instruction manual
A truss could be described a framework of materials acting primarily in compression and tension. Being light in weight, a truss is a very stiff form of construction and that is the reason why it is used in construction. Wooden trusses the most common types used in building and construction industry today because they are cheap and requires less labor and experience to construct (MiTek 3). Roofing…