Got a tricky question? Receive an answer from students like you! Try us!

Contracts - Coursework Example

Only on StudentShare
Author : casperona

Summary

Contracts Coursework 10/20/2012 Executive Summary The recommendation described below reflects the assessment of this author based on the provisions indicated by the NEC3-ECC contract frame work. I shall describe an alternative framework that may provide more understanding and coverage as far as ensuring project completion…

Extract of sample
Contracts

The consultant’s documents were submitted on time, planning permissions gained and quotes received from various contractors. The project was awarded under NEC3-ECC conditions of contract. The Project duration was agreed to be 26 months and payment to the contractor through interim valuations. The project was delayed due to late payment, lack of workmen on site, work behind schedule and late project administrator’s instructions. The contention between the parties was about payment, contractual standing of contractor’s program and principle guiding claim and dispute resolution. The project ran into great difficulties after the 10th month, accusation were exchanged, agreed payments not made and the workmen were pulled off site by the contractor which led to dispute. Table of Contents Executive Summary 1 Table of Contents 2 Introduction 3 General Principle of Construction contracts 4 Dispute resolution guidelines 5 Comparable Analysis of NEC3-ECC, JCTO5 SBC/Q 6 NEC3-ECC 8 JCTO5 SBC/Q 9 Clear Difference 10 Recommended Approach 11 References/Bibliography 14 Introduction AOS Development is a national housing development company in Edinburgh and has embarked on eighty housing units developments in Skye, Scotland. The consultant’s documents were submitted on time, planning permissions gained and quotes received from various contractors. ...
Download paper

Related Essays

An organizational structure of an engineering and construction company
The paper tells that like any other company, all companies need to have an organizational structure to help in running it effectively. For example, a company operates and executes its services and products to its clients. As an engineering and construction company, it has to have a large scope with several employees on board that will befit its aim and objectives. The structure presented in the paper will fundamentally fit into an outstanding engineering and construction company, where co-ordinator is given weak power and much power given to engineering and construction departments.…
11 pages (2761 words)
Re-negotiations in PPP Transport Infrastructure
The paper tells that there is the tendency of national governments to incorporate the public-private partnerships (PPP) to provide and upgrade infrastructures, as well as public services. Talk of light rails, upgraded electric railway system, mainland road and main highways, as well as port facilities, are just but some of the projects the private sector is getting substantially involved in, conjunction with the public and local authorities to enhance service delivery in the transport system. Majority of these engagements are made effective via a group of diverse companies and contractual…
20 pages (5020 words)
Design-build and Design-Bid-Build Contracts: Their Advantages and Disadvantages
The design-build and design-bid-build are the two forms of contracting in this regard that are most commonly considered while planning for a construction project. While the design-build is a traditional method, the other is an alternative form of contracting involving greater complicacies. Also, these two systems have their respective advantages and disadvantages that can significantly affect the effective completion and quality of work. This particular study thus considers the concept of these two contracting systems and discusses about the advantages and disadvantages of both the systems of…
11 pages (2761 words)
NEC3
As a contract administrator you have been tasked to produce a report explaining how the NEC3 Contract works and how it differs from the JCT2011 Contracts highlighting the possible implications for administering a project with the NEC3. Introduction New Engineering Contracts 3rd Edition or NEC3 is a modernistic family of contracts of contracts. It helps in implementing construction project management and supervisory principles. NEC3 synchronises the different business and engineering practices and also renders definitions for the different legal relationships and liabilities. Hence, adoption of…
4 pages (1004 words)
NEC ECC Contracts
General Construction. Contract Principles The Housing Grants, Reconstruction and Regeneration Act 1996 (HGRRA) focuses on payments under a construction contract. Specifically, the Act states that, when a construction contract is for 45 days or more that the party to the construction contract is entitled to installment payments (HGRRA 1996 §109). Section 111 of the HGRRA 1996 states that a construction contract shall stipulate the dates of the payments, and when the final sum comes due. Section 112 forms the basis on when and why one party may not pay the other party. Local Democracy, Economic…
12 pages (3012 words)
Procurement & Contracts Coursework
57). One of the key attributes of PPP is that it not only facilitates public-private partnerships during the construction phase, but it provides for post-construction services to be managed by a private agency. It has been argued that by taking this approach, the construction design is usually conducted contemplating subsequent services which ultimately lowers the cost of services. Moreover, the nature and duration of the PPP encourages a relationship of trust and facilitates the free flow of information (Hoppe & Schmitz, 2013). Likewise, Private Finance Initiative (PFI), project procurement,…
23 pages (5773 words)
Wooden truss
Wooden trusses the most common types used in building and construction industry today because they are cheap and requires less labor and experience to construct. Roofing materials are designed to support various building loads. In addition, trusses come in various shapes and sizes In selecting any material, it is necessary to put into consideration a number of factors including cost, performance, safety and regulation. The following materials are needed during the construction of a wooden roofing truss. A research should be conducted to ensure that the designed truss suits the project or…
4 pages (1004 words)