Contract Administration Coursework example
Undergraduate
Coursework
Engineering and Construction
Pages 10 (2510 words)
Download 0

Introduction

University Name: East London Department: Architecture, Computing & Engineering Student’s Name: Unit/Unit Number/Title: CE 2218 Contract Administration Title of the piece of Work: Tort: Trespass/Nuisance. ...
Download paper
Not exactly what you need?

Related papers

Roles & Responsibilities
Since they are professionals, they also affiliate with other professionals in order to gain certain information or to achieve particular goals. They work closely with structural engineers, who give detailed information about design certain areas like the column, rely on the building engineers who interpret the drawing and implement it, and architect also partner with plumbers and electrical…
Contracts
The consultant’s documents were submitted on time, planning permissions gained and quotes received from various contractors. The project was awarded under NEC3-ECC conditions of contract. The Project duration was agreed to be 26 months and payment to the contractor through interim valuations. The project was delayed due to late payment, lack of workmen on site, work behind schedule and late…
Pre-Contract Cost Planning and Cost Controlling
Cost planning not only enables capital cost budgets to be set but also provides a structure to accommodate as well as manage transformations to the client’s brief and design (Murdoch & Hughes, 2007, p.80). An effective Cost plan enables a client together with the design team to understand where and how finances have been allocated towards the completion of a project. On the other hand, Cost…
contract adminstration report
It also explains the reasons why the employer should include them in the contract. Offsite Materials Bonds: Offsite materials include all listed items in the contract which have not been delivered to or close to the site of the project. These materials are insured by offsite material bond. Therefore, the inclusion of this bond in the contract insures the employer against the losses incurred for…
coursework 2
The project must be delivered within the stipulated time and within the projected budget cost. Such expectations with time require strict operation and ultimate discipline especially with procurement and implementation. Considerations when Accepting a Contractor’s Work Programme When evaluating the possibility of accepting a contractor’s work programme in regard to a construction project,…
Contract
There are six milestones: Materials (90 days) Construction work (2.5 years) Construction/ handicraft work (21/2years) Installation work (23/4 years) Restoration/clean-up of project site (After 3 years) Other work (After 3 years) Article 3 Sub article 3.5 6. What is the amount of liquidated damages for each day that each milestone is late? 0.5 % of the total contract for each day Article 6…
Project Administration in Construction
Good project managers attempt to make sure that the work is done right first time and that key accidents take place on the project. Whilst adherence to subsisting design decisions is the key concentration of quality regulation, there are exceptions to this standard. To begin with, unexpected circumstances, inaccurate design decisions or transformations needed by an owner in the facility purpose…