Contract Administration - Coursework Example

Only on StudentShare

Extract of sample
Contract Administration

University Name: East London Department: Architecture, Computing & Engineering Student’s Name: Unit/Unit Number/Title: CE 2218 Contract Administration Title of the piece of Work: Tort: Trespass/Nuisance. ...
Download paper

Related Essays

Engineering and Construction: Roles and Responsibilities; Health and Safety Legislation
This research will begin with the statement that an architect is person trained to design structures like buildings, roads and dams while architecture is the use of the knowledge acquired through study experience and practice in the solving of an engineering problem. Architect obtains raw facts from the client and develops them to information that can be interpreted by various personnel in the construction field. He participates in the building process throughout, from planning to occupancy. He is also known as the lead consultant and chairs all the site meetings. Since they are professionals,...
14 pages (3514 words) Essay
Contracts
The consultant’s documents were submitted on time, planning permissions gained and quotes received from various contractors. The project was awarded under NEC3-ECC conditions of contract. The Project duration was agreed to be 26 months and payment to the contractor through interim valuations. The project was delayed due to late payment, lack of workmen on site, work behind schedule and late project administrator’s instructions. The contention between the parties was about payment, contractual standing of contractor’s program and principle guiding claim and dispute resolution. The project...
12 pages (3012 words) Coursework
Pre-Contract Cost Planning and Cost Controlling
Cost planning not only enables capital cost budgets to be set but also provides a structure to accommodate as well as manage transformations to the client’s brief and design (Murdoch & Hughes, 2007, p.80). An effective Cost plan enables a client together with the design team to understand where and how finances have been allocated towards the completion of a project. On the other hand, Cost control should be provided from start to completion of the project, ensuring that the estimated final cost is always known. However, Pre-contract Cost Controlling is quite different from the Post-contract...
9 pages (2259 words) Assignment
contract adminstration report
It also explains the reasons why the employer should include them in the contract. Offsite Materials Bonds: Offsite materials include all listed items in the contract which have not been delivered to or close to the site of the project. These materials are insured by offsite material bond. Therefore, the inclusion of this bond in the contract insures the employer against the losses incurred for non delivery of materials. This problem arises when the employer has made full payment to the contractor for procumbent of materials, but the contractor has failed to deliver the materials to or...
8 pages (2008 words) Book Report/Review
coursework 2
The project must be delivered within the stipulated time and within the projected budget cost. Such expectations with time require strict operation and ultimate discipline especially with procurement and implementation. Considerations when Accepting a Contractor’s Work Programme When evaluating the possibility of accepting a contractor’s work programme in regard to a construction project, various points must be considered. Ashworth (2006) asserts that the key concerns towards the acceptance of the programme will be considered in the pre-construction conference. During this conference, I as...
5 pages (1255 words) Essay
Contract
There are six milestones: Materials (90 days) Construction work (2.5 years) Construction/ handicraft work (21/2years) Installation work (23/4 years) Restoration/clean-up of project site (After 3 years) Other work (After 3 years) Article 3 Sub article 3.5 6. What is the amount of liquidated damages for each day that each milestone is late? 0.5 % of the total contract for each day Article 6 Sub-article 6.7 7. Does the government have the right to occupy a completed part of the work? No 8. How long does the contractor have to perform the entire project? 1095 days from day of signing of contract...
3 pages (753 words) Assignment
Project Administration in Construction
Good project managers attempt to make sure that the work is done right first time and that key accidents take place on the project. Whilst adherence to subsisting design decisions is the key concentration of quality regulation, there are exceptions to this standard. To begin with, unexpected circumstances, inaccurate design decisions or transformations needed by an owner in the facility purpose may need re-examination of design at the time of construction. Whilst these transformations might be influenced by the issue for quality, they stand for the occasions for re-design with all the...
4 pages (1004 words) Essay
Got a tricky question? Receive an answer from students like you! Try us!