EXPENDITURE PLANNING AND CONTROL Essay example
Masters
Essay
Engineering and Construction
Pages 7 (1757 words)
Download 0
CONTENTS PAGE I. Introduction…………………………………………………… …2 II. Background Facts.………………………………………….2 III. Analysis of the Issues…

Introduction

Conclusion......................................................................................13 Appendix A: Time and Cost Calculation................................................15 Appendix B: Preliminaries cost due to the Prolongation of the Works. 15 References 16 Bibliography 17 Expenditure Planning and Control – Assignment 1 I. Introduction I have been instructed by the main contractor (‘the Contractor’) to prepare a report in relation to a construction project which has experienced significant problems from the get go, which have resulted in delay and disruptions during the course of the Works. These delays and disruptions have inevitably affected the Contractor’s ability to complete the work in a timely fashion. This report provides an independent assessment of the surrounding particulars and contract documentation with a view to resolving the matter. I have specifically been instructed to include in the report the following points: an analysis of the delays; extension of time (‘EOT’); liquidated damages; valuation of work and claims for loss and / or expense. Generally speaking, I am instructed to provide my opinion in relation to the parties’ rights and obligations under the contract. The report begins by outlining in brief the ‘Background Facts’ and issues which arose (see section II). Section III of the report provides an ‘Analysis of the Issues’. Under this section, each problem is addressed in chronological order. ...
Download paper
Not exactly what you need?

Related papers

Development Appraisal, Project Cost Control
The building and construction sector includes contractors who build buildings for residential, industrial and commercial purposes. SECTION-A Question 1 This is a case whereby companies operating in the construction industry need to develop, differentiate, defend and communicate the development contribution they make to their host country  in just the same way as they manage the value they…
Construction Cost Control & Management
In our case, the formula is; (a + 4 m + p) / 6 (NetMBA, 2012). Where, O = Optimistic Time. M = most likely time. N = pessimistic time. Activity a days m days b days Expected Days a 4 m p (a + 4 m + p) / 6 AB 4 5 6 (4 + (4 *5) + 6) / 6 = 5 BC 2 5 8 (2 + (4 *5) + 8) / 6 = 5 CD 5 7 9 (5 + (4 *7) + 9) / 6 = 7 CE 4 5 6 (4 + (4 *5) + 6) / 6 = 5 DF 2 4 6 (2 + (4 *4) + 6) / 6 = 4 FG 3 5 9 (3 + (4 *5) + 9)…
Statistical Process Control
There are many factors that affect the scenario like mental focus, body strength, direction of air, kick intensity, shoe structure and level of tiredness etc. Despite these factors the players are selected in teams for their marksmanship. The question that arises here is that if a player cannot exhibit exactly same performance again and again then what the criterion of a player selection is? The…
Strategic Planning
It is therefore needed for the proper programming of work structure and proceeding as it provides a clear formula for the problem solving. Strategic planning gives a new structure and outline for the steps to be undertaken in an organization to prevent any misfortune which might come on the way as they carry out their activities. A good strategic plan is one that can allow for the reengineering of…
Process Control Project
It shows that the steam reduced by 45% as time moved on. This means, there is energy conservation by the system. Such control is made possible by the application of information technology. The following is the logical flow of the feedback control loop. Flow Diagram for a Feedback Control Loop Temperature Control for a Heat Exchanger Whereby the fluid entered the system from different sides of the…
Pre-Contract Cost Planning and Cost Controlling
Cost planning not only enables capital cost budgets to be set but also provides a structure to accommodate as well as manage transformations to the client’s brief and design (Murdoch & Hughes, 2007, p.80). An effective Cost plan enables a client together with the design team to understand where and how finances have been allocated towards the completion of a project. On the other hand, Cost…
process control
This flow is usually expressed by plotting the valve travel on the (y-axis) against the flow percentage under constant pressure differential on the (X-axis). There are two main types of the inherent flow characteristics; these are linear and equal percentage. A control valve is said to be linear if its inherent flow characteristics can be represented on a graph by a straight line. The flow is…