StudentShare solutions
Triangle menu

Construction Cost Control & Management - Coursework Example

Not dowloaded yet

Extract of sample
Construction Cost Control & Management

Activity Duration in days Earliest start time Latest start time Total float AB 5 0 0 0 BC 5 5 6 1 CD 7 11 11 0 CE 5 11 11 0 DF 4 18 18 0 FG 5 22 22 0 FH 5 22 22 0 FI 4 20 22 2 FJ 7 22 22 0 JK 11 29 29 0 KL 6 40 40 0 KM 8 40 40 0 MN 5 48 48 0 LO 7 46 46 0 OP 6 53 53 0 PQ 3 59 59 0 2 (a) How the Contract Sum can be adjusted in accordance with the JCT form of contract JCT means Joint Contracts Tribunal, the bylaw applied to contractors and architects in fulfillment of contract conditions. According to Article 2 of the JCT contract forms, the contractor is given an option of adjusting the contract sum as per the agreement in the contract form. The sum of money in the form is exclusive of VAT, meaning that, the payment of VAT can be added to the sum if necessary. The extent to which it affects the contractor depends on his or her ability to reclaim the VAT money. According to Clause 5.2, the contractor can reclaim the contract sum in regard to work and labor involved in the contract (Neil, Baylis, 1999). The fact that the economy does not remain constant might bring a lot of complications in the contract. Changes in the value of currency and inflation are unpredictable and, therefore; one side of the parties involved might end up losing while the other one gains substantially. It is due to this reasons that certain formulas are provided to calculate the fluctuations. Although the contracts are based on fixed prices, adjustments are done in regard to changes in levies, taxes and duties imposed to the contract materials, tools, equipments and machineries. However, careful drafting and contract sum analysis must be done to facilitate effective amendment and adjustments when the...
In conclusion of the research, the PERT chart has been critically used to schedule, organize, and coordinate the tasks in this project. It has effectively ascertained the expected time of the project for effective planning and accountability of time and estimation of resources and cost. From the analysis, the pessimistic, normal and optimistic time were estimated. This was critical in showing the various activities keeping in mind their dependence to each other and particular independence. From the analysis with help of the PERT diagram, the critical path procedure shows that the estimated longest time to complete the project will be 63 days. The NPV of projects X and Y were found to be 20.60 and 1041.90 respectively. The excavator used during the project should not be more than 5 years old, this for efficiency purposes and minimization of loss. With respect financial analysis, the tender documents of the contracting organization ought not to be complicated. The standard nature of the documents will ascertain the value of the credit and cash flow of the contract period. The currency of operation is also critical in the sense conversion rate; therefore if contractor and employer are working on different currencies, risk measures should be taken into account prior to tendering and signing of contract. Consequently, issues prompting increment of project value have been discussed and shown clearly how the contractor can claim for additional cash. This is imperative for loss minimization in the process of project implementation. ...Show more

Summary

The purpose of this paper is to evaluate and present Construction Cost Control and Management. For achieving this present paper will attempt to illustrate the PERT diagram; expected time for each activity; the significance of the critical path and total float. …
Author : xbeier
Construction Cost Control & Management essay example
Read Text Preview
Save Your Time for More Important Things
Let us write or edit the coursework on your topic
"Construction Cost Control & Management"
with a personal 20% discount.
Grab the best paper

Related Essays

The Influence of Language and Cultural Barriers in Project Management Effectiveness among Construction Companies in UAE: An Empirical Study
Abstract The present research aims to determine the influence of cultural and language barriers on project management effectiveness among Southeast Asian migrant workers in the UAE. 126 migrant workers were purposively sampled for the study. The statistical findings show that the respondents are not certain about roles and status as a source of conflict within the project management context of the UAE construction industry.
50 pages (12500 words) Coursework
Sustainable Construction Method
The research objective is to evaluate and present the environmental impact of construction works and demonstrate modern methods of construction. It also provides a review of zero and low available option of carbon energy which aims at meeting the criteria of the city of the council in which the school is to be constructed.
13 pages (3250 words) Coursework
Construction Cost Control & Management
Groundwork; the foundation of the construction site and the separate pits of the stanchion bases is to be dug by use of a loader backhoe and a wheeled excavator. The time it will take to prepare the site will be a maximum of two weeks excluding Sundays. The area that is to be excavated is the perimeter of the whole area the lodge will occupy.
10 pages (2500 words) Coursework
Construction Management
This agreement has to be signed by both parties to allow for compliance during the whole construction process. Every construction process requires a system to procure the construction services, to be able to identify the correct system needed for any construction services; one has to be able to know the size of the project.
4 pages (1000 words) Coursework
Cost and financial management
The objective of preparing this report is to measure the performance of this company and make a comparison of the same with the general industry. This paper will also analyze the performance of a competitor of WS Atkins with the aim of comparing the evaluation.
16 pages (4000 words) Coursework
Management accounting and control
This has prompted the use of the balance scorecards approach which enables the organizations to balance the internal and process measures with results and the financial measures which gives the managers a complete picture of the organization as well as the areas where they should make improvements (Lipe and Salterio 2000).
15 pages (3750 words) Coursework
Chinese Construction Industry
It provides guidance for implementing a risk control strategy that is appropriate to control construction projects at all levels. This paper will review systematic management approaches to risk. It discusses the allocation of risk and suggests that risk needs to be identified and managed early in the procurement process.
40 pages (10000 words) Coursework
Construction Management
With this in mind, the following analysis will be focused upon the issue of human resource management as it relates to the construction industry on a global scale. Accordingly, the initial discussion will analyze existing human
9 pages (2250 words) Coursework
Applied Construction Management
The constructed car park will be of essence since the off street parking is limited to a maximum of an hour (Arnold, 2012). As per the feasibility study that was conducted by the international car
14 pages (3500 words) Coursework
Supply chain management plan in construction project
The strategy lies in proper linking of the all stakeholders in material movement process ensuring that there is no break at any point of material transfer or material shortage whatsoever.
6 pages (1500 words) Coursework
Get a custom paper written
by a pro under your requirements!
Win a special DISCOUNT!
Put in your e-mail and click the button with your lucky finger
Your email
YOUR PRIZE:
Apply my DISCOUNT
Comments (0)
Rate this paper:
Thank you! Your comment has been sent and will be posted after moderation