contract adminstration report - Book Report/Review Example

Extract of sample
contract adminstration report

It also explains the reasons why the employer should include them in the contract. Offsite Materials Bonds: Offsite materials include all listed items in the contract which have not been delivered to or close to the site of the project. These materials are insured by offsite material bond. Therefore, the inclusion of this bond in the contract insures the employer against the losses incurred for non delivery of materials. This problem arises when the employer has made full payment to the contractor for procumbent of materials, but the contractor has failed to deliver the materials to or adjacent to the works. Hence, the bond guarantees compensation for the losses irrespective of the dispute between the employer and the contractor. This also extends to whether no action is taken against the contractor or any extension given to the contractor. Under SBC/XQ rules, the employer pays the amount of listed items in the contract prior to delivery on or next to the works. The contractor then is expected to insure these materials against losses, damages thus protecting the interest of employer. This protection begins from the time the property is transferred to the contractor to the time they are delivered to or close to the site. The amount of bond only covers the listed items which have not been delivered. Where materials are not delivered, the employer makes a claim in writing to the surety. ...
Download paper

Summary

CONTRACT ADMINISTRATION REPORT By Name: Course: Instructor: University: Physical Address: Date: Introduction: The Joint Contracts Tribunal’s Standard Building Contracts provides guidelines and rules for formulating and administering contracts within the construction sector in United Kingdom…
Author : tyrese30
Download 1

Related Essays

Contract Administration
University Name: East London Department: Architecture, Computing & Engineering Student’s Name: Unit/Unit Number/Title: CE 2218 Contract Administration Title of the piece of Work: Tort: Trespass/Nuisance.
10 pages (2510 words) Coursework
Pre-Contract Cost Planning and Cost Controlling
Cost planning not only enables capital cost budgets to be set but also provides a structure to accommodate as well as manage transformations to the client’s brief and design (Murdoch & Hughes, 2007, p.80). An effective Cost plan enables a client together with the design team to understand where and how finances have been allocated towards the completion of a project. On the other hand, Cost control should be provided from start to completion of the project, ensuring that the estimated final cost is always known. However, Pre-contract Cost Controlling is quite different from the Post-contract...
9 pages (2259 words) Assignment
Engineering - Steel Report
According to Degarmo and Black (2003, p.56), reinforced bars with high ductility and tensile strength are often preferred because they allow the materials to be rolled, drawn or made longer without breakage. Generally the tensile strength of reinforcing steel can be measured by dividing the cross sectional area of the steel tested by the stress exerted on the material. The amount of stretching force (N) needed to break the test material can then be measured and recorded. Experimental Procedure The tensile testing experiment involved calculating mechanical properties of three specimen samples...
5 pages (1255 words) Lab Report
report 1
This plot is known as the grain distribution plot and will be used for purposes of this report. More often, a relatively distributed curve shows well graded or a soil which is poorly sorted whilst an extremely steep distribution curve, a curve with steep distribution shows poor grade or sufficiently sorted soil. Objectives of the experiment This lab was developed to determine the distribution of grain size for Concrete & Asphalt materials. This is achieved by determination of the coefficient of uniformity, as well as the coefficient of curvature, . These describe general slope and shape of the...
3 pages (753 words) Essay
Report
However some technical problems such as weight of the arm and unforeseen parameters of the robot going out of the maze were encountered in execution of the project. The objective of the project is to enable a robot to look for a ball and pick it up while avoiding black lines. The goal is divided into a logical sequence that enables the robot to achieve its goal. The sequence flow is as follows. The necessary parameters for the robot are set, these include the sensors and motors that enable the robot to move. The robot then looks for a ball. It then estimates and determines the distance to the...
6 pages (1506 words) Lab Report
Contract
There are six milestones: Materials (90 days) Construction work (2.5 years) Construction/ handicraft work (21/2years) Installation work (23/4 years) Restoration/clean-up of project site (After 3 years) Other work (After 3 years) Article 3 Sub article 3.5 6. What is the amount of liquidated damages for each day that each milestone is late? 0.5 % of the total contract for each day Article 6 Sub-article 6.7 7. Does the government have the right to occupy a completed part of the work? No 8. How long does the contractor have to perform the entire project? 1095 days from day of signing of contract...
3 pages (753 words) Assignment
I-35 Bridge report
Finally, the report also focuses on the rehabilitation “of the I-35W Bridge” and practices that have been adopted in the construction and maintenance of bridges. It shows how various organizations in fire and emergence, law enforcement and environmental monitoring, can reduce the impact of a possible tragedy like that of the collapse of I-35W Bridge to cause minimal loss of lives and property. Table of contents 1. Introduction 2. I-35W bridge maintenance and construction 3. Emergency Assistance after the Collapsed Bridge 4. Impact “of the I-35W Bridge Collapse on the Current Practices”...
5 pages (1255 words) Research Paper
Got a tricky question? Receive an answer from students like you! Try us!