Construction Law Essay example
Masters
Essay
Engineering and Construction
Pages 10 (2510 words)
Download 0
There are several problems and issues that surfaced in this project’s life cycle and each has a different domain as per JCT 2005 Standard form of Building contract. These issues are discussed in detail in their chronological order. The first among which is regarding the fact that the contractor noticed a contradiction between drawing and BOQ but assuming that drawings were right, conducted the work accordingly…

Introduction

Where as in this case the contractor did not take any consent from the CA. Hence the CA/Architect is not responsible neither bound to pay for any additional claims in the BOQ and Interim Payment Certificate. But the above conditions and clauses are only applicable if the contractor becomes aware of the conflicting documents. The second issue of alteration of position of brackets that are already fixed. In light of the JCT contract, I am of the opinion that the contractor does not have the capacity to refuse the CA/Architect of any redo of work or variation in the design/construction, until the contractor has been issued a completion certificate or in case the work ordered by the CA/Architect is out of his authority. In any other case contractor is bound to follow the instruction and variation made by CA. whereas if the particular activity is on the critical path then contractor can claim an extension in the deadline, along with a reasonable compensation of performance of the particular task. The clause 5.6 deals with all the rules that are applicable in case of a variation in work. Whereas on the other hand contractor is contractually bound to show compliance to any instruction that is given by the CA/Architect under the clause 3.10.1/2. ...
Download paper
Not exactly what you need?

Related papers

Construction Economics
The industry provides services such as maintenance, repairs and rehabilitation of existing structures. …
Construction Law
The ECS contract is parallel to ECC in detail and complications of contractual demands; however, the names of the parties to the contract and timescales for completion are changed to meet the deadlines under the ECC contract (GMH Planning, 2012). Clause 11.2(17) lays down the criteria for a subcontractor. Firstly, someone involved in construction or installation of part of the work which indicates…
Construction law essay
It must be emphasized that the loss or injury suffered by the claimant must be of consequential nature. In other words, the loss must be the result of the damaged or defective nature of the property and not the damage to the property itself. When a party has acted negligently which results in a defective property, there is only pure economic loss which is not actionable under tort laws. They may…
CONSTRUCTION LAW - YEAR 3 IN QUANTITY SURVEYING
The size of your project demands that you will need to employ a full time CDM coordinator too. The CDM coordinator will be responsible for compliance with CDM regulations. CDM 2007 stipulates that the CDM coordinator must be a competent person. Moreover, CDM 2007 expects that all parties involved in the project will cooperate and coordinate with each other. All involved parties are also stipulated…
Construction Health and Safety
Otherwise, any designer who may be engaged by a domestic client is obliged to comply with the rules. Construction works refer to construction alteration, upkeep, repair and maintenance, commissioning, renovation, decommissioning, redecoration, fitting-out, demolition or dismantling. It also includes site preparation, exploration and surveys. Failure to comply with the code is treated as evidence…
Sustainable Construction, Management and Professional Studies
Moreover, there is also need to ensure that the repair works goes on well in accordance to the design. These expectations will actually be guided by the contracts between Uxbridge Water plc and the designer as well as the contractor for repair works. Consequently, this report outlines the procedure that will be used during the procurement and contract matters for the repair works. Procurement…
health and safety in construction
Through this many industries will be able to prevent the occurrences of accidents in the workplace. The industries should also be ready to compensate anyone when he has been in involved in such accidents. This can lead to most people being able to be employed in this sector as most of the people are unemployed and also are not ready to work in construction companies. The health sector should also…