StudentShare
Contact Us
Sign In / Sign Up for FREE
Search
Go to advanced search...

The project chosen for the is the house construction - Assignment Example

Cite this document
Summary
The project chosen for the assignment is the house construction. This project required the completion of following activities that needed the duration specified according to the nature of tasks involved in each of them.
Foundation: This is the primary work in the whole process…
Download full paper File format: .doc, available for editing
GRAB THE BEST PAPER92.9% of users find it useful
The project chosen for the assignment is the house construction
Read Text Preview

Extract of sample "The project chosen for the is the house construction"

Download file to see previous pages

The time required is only 8 days. The time allocated was 10, which would be on a higher estimation. The major activity is only the fixing the roof components to the wall frames and placing the skylights. The necessary designs for the skylights could be prepared and fabricated early. Placing this could be undertaken along with the roof work. And the attaching the TV antenna shall also be undertaken along with this. Plumbing and wiring: The plumbing and wiring could be simultaneously undertaken and requires 4 days each for this activity.

As the it involves only fixing up of he components 6 days of plumbing could be reduced to 4 days as equivalent that of wiring. Plastering: plastering work need to be undertaken after the plumbing and wiring, as any damages to the structure could be rectified at this stage. 4 days would be enough for this operation as it involves only covering the walls with appropriate mortar. Foundation:, Frames: 14 December 2008, Roof: 22 December 2008, Skylight: 25 December 2008, TV antenna - 28 December 2008, Plumbing and wiring: 30 December 2008; Plastering: 3 January 2009; Finishing: 7 January 2009, Painting: 7 January 2009; Carpets, curtains and sides: 13 January 2009 and landscape: 15 January 2009.

The critical activities that would effect the shorted time required to complete the project are foundation, frames, roof,. The other two days could be used for the actual operation. Stage 2 : TV Dummy Foundation Frames Roof Skylight Wiring Plastering Dummy plumbing (e) You will need to list the critical activities in your project and explain why they are critical, you will need to list the activities that are non critical and explain why.

( answer why ). The critical ActivitiesActivityStart dateDurationFoundation8 December 20086Frames14 December 20088Roof22 December 20088Plumbing and wiring30 December 20084Plastering3 January 20094Finishing7 January 20094Painting7 January 20096These activities are considered critical because the minimum duration required for the project to be completed is along this path only.Non Critical activitiesActivityStart dateDurationSky light25 December 20082TV antenna28 December 20081Carperts, curtains13 January 20093Land scape13 January 20094They are considered non-critical because further reduction of their time don't reduce the overall project duration.

They could be undertaken simultaneously with the critical events.Foundation:, Frames: 14 December 2008, Roof: 22 December 2008, Skylight: 25 December 2008, TV antenna - 28 December 2008, Plumbing and wiring: 30 December 2008; Plastering: 3 January 2009; Finishing: 7 January 2009, Painting: 7 January 2009; Carpets, curtains and sides: 13 January 2009 and landscape: 15 January 2009.The critical activities that would effect the shorted time required to complete the project are foundation, frames, roof, plumbing,

...Download file to see next pages Read More
Cite this document
  • APA
  • MLA
  • CHICAGO
(“The project chosen for the assignment is the house construction”, n.d.)
The project chosen for the assignment is the house construction. Retrieved from https://studentshare.org/miscellaneous/1506901-the-project-chosen-for-the-assignment-is-the-house-construction
(The Project Chosen for the Assignment Is the House Construction)
The Project Chosen for the Assignment Is the House Construction. https://studentshare.org/miscellaneous/1506901-the-project-chosen-for-the-assignment-is-the-house-construction.
“The Project Chosen for the Assignment Is the House Construction”, n.d. https://studentshare.org/miscellaneous/1506901-the-project-chosen-for-the-assignment-is-the-house-construction.
  • Cited: 0 times

CHECK THESE SAMPLES OF The project chosen for the assignment is the house construction

Shell Company's Efforts, Actions, and Initiatives Regarding Sustainability

1st is the GREEN house REGULATION.... [SHELL] [University] [Instructor Name] “Shell company's efforts, actions and initiatives regarding sustainability” The company that has been chosen is Shell Limited.... It is an international organization, that has been functioning well despite facing a huge number of lawsuits and allegations, their profits have not dwindled....
7 Pages (1750 words) Assignment

What Makes a Good Leader

the house was for an elderly couple.... the house was to be built on a rocky land measuring 3000 Sq ft.... in Fort Worth and I started designing the house in 2011 to be delivered by the end of 2012.... I was the chief designer for the project responsible for making the house plan, getting approval from local agencies and heading a team consisting of building contractor who would be building the house and a team of supervisors and subcontractors for various works such as plumbing, electricians, etc....
12 Pages (3000 words) Assignment

Aspects of Contracts and Negligence

For example a contract for a contractor to install doors and windows in a dwelling house for a site owner who leases the house to tenants will impact the tenants.... In the installation of windows and doors, the tenants will be subjected to disruptions and interruptions in their daily lives as the construction takes place....
18 Pages (4500 words) Assignment

Health Promotion in Hillfields

In this assignment, the health profiling of the area of Hillfields in the locality will be done to identify the extent of opportunities for health and lifestyle improvement in that locality.... In this assignment, the profiling of Hillfields has been presented.... This area was chosen since this is a small locality with recent developments and a structured attempt to improve the health of this area.... Most of such interventions are designed as a project or a programme guided by policies....
4 Pages (1000 words) Assignment

Building Performance

This paper ''Building Performance'' tells that This involves the reduction of waste the in-construction process.... This is capable of reducing the construction costs as the recycled material can be used in other constructions.... If the cling was a nonendothermic firm, the builder can sell the construction waste.... hellip; If the builder is big enough and is having own recycling process unit, he can use the recycled material in other constructions and can save investment on the constructions, which again reduces the construction costs....
18 Pages (4500 words) Assignment

Effective Project Planning and Management

This part of the assignment presents a general discussion on project management and quality related concepts.... This paper "Effective project Planning and Management" discusses the theoretical framework for project management.... I will make use of them to monitor and control the progress of this project.... We will make use of Work Breakdown Structure (WBS) and CPA for effective management of major project resources and procedures....
8 Pages (2000 words) Assignment

Usability Engineering

Therefore, the research work will involve two main but separate parts which are interrelated but will be very crucial in the project.... Scope the project will explore a number of areas in regard to the site ranging from the membership of the community, activities of the members, the interests of the community members, the kind of activities carried out in the site, the number of members in the site and the bulk of the work done by the members.... ov assignment Part 3 Usability Engineering Website (www…) //Edit the Table of Contents Executive Summary 1Introduction 2Description/Overview of site 2Scope 2 Test Objectives 2Method 3 Participants 3 Context of Site/Application Use in Test 3 Tasks 3 Test Facility 3 Participants Computing Environment 3 4 Experimental Design 4Procedure 4Participant Task Instructions 4 Usability Metrics 5Results 5 Data Analysis 5 Data Scoring 5 Data Reduction 6Presentation of Results 6a) One or more measures of user satisfaction....
1 Pages (250 words) Assignment

Health and Safety in Construction and Built Environment

… The paper "Health and Safety in construction and Built Environment" is a wonderful example of an assignment on engineering and construction.... It was on April 06, 2007, that The construction Regulations, popularly known as CDM2007, came into force.... These guidelines replaced CDM94 or construction regulations 1994 and CHSW or construction (Health, safety, and Welfare) Regulations of 1996.... The paper "Health and Safety in construction and Built Environment" is a wonderful example of an assignment on engineering and construction....
21 Pages (5250 words) Assignment
sponsored ads
We use cookies to create the best experience for you. Keep on browsing if you are OK with that, or find out how to manage cookies.
Contact Us