StudentShare solutions
Triangle menu

The project chosen for the is the house construction - Assignment Example

Not dowloaded yet

Extract of sample
The project chosen for the is the house construction

The time required is only 8 days. The time allocated was 10, which would be on a higher estimation. The major activity is only the fixing the roof components to the wall frames and placing the skylights. The necessary designs for the skylights could be prepared and fabricated early. Placing this could be undertaken along with the roof work. And the attaching the TV antenna shall also be undertaken along with this.
Plumbing and wiring: The plumbing and wiring could be simultaneously undertaken and requires 4 days each for this activity. As the it involves only fixing up of he components 6 days of plumbing could be reduced to 4 days as equivalent that of wiring.
Plastering: plastering work need to be undertaken after the plumbing and wiring, as any damages to the structure could be rectified at this stage. 4 days would be enough for this operation as it involves only covering the walls with appropriate mortar.
Foundation:, Frames: 14 December 2008, Roof: 22 December 2008, Skylight: 25 December 2008, TV antenna - 28 December 2008, Plumbing and wiring: 30 December 2008; Plastering: 3 January 2009; Finishing: 7 January 2009, Painting: 7 January 2009; Carpets, curtains and sides: 13 January 2009 and landscape: 15 January 2009.
The critical activities that would effect the shorted time required to complete the project are foundation, frames, roof,...
The other two days could be used for the actual operation.
Stage 2 :


TV
Dummy
Foundation Frames Roof


Skylight Wiring Plastering
Dummy plumbing

(e) You will need to list the critical activities in your project and explain why they are critical, you will need to list the activities that are non critical and explain why. ( answer why ).


The critical Activities
Activity
Start date
Duration
Foundation
8 December 2008
6
Frames
14 December 2008
8
Roof
22 December 2008
8
Plumbing and wiring
30 December 2008
4
Plastering
3 January 2009
4
Finishing
7 January 2009
4
Painting
7 January 2009
6

These activities are considered critical because the minimum duration required for the project to be completed is along this path only.
Non Critical activities
Activity
Start date
Duration
Sky light
25 December 2008
2
TV antenna
28 December 2008
1
Carperts, curtains
13 January 2009
3
Land scape
13 January 2009
4

They are considered non-critical because further reduction of their time don't reduce the overall project duration. They could be undertaken simultaneously with the critical events.
Foundation:, Frames: 14 December 2008, Roof: 22 December 2008, Skylight: 25 December 2008, TV antenna - 28 December 2008, Plumbing and wiring: 30 December 2008; Plastering: 3 January 2009; Finishing: 7 January 2009, Painting: 7 January 2009; Carpets, curtains and sides: 13 January 2009 and landscape: 15 January 2009.
The critical activities that would effect the shorted time required to complete the project are foundation, frames, roof, plumbing, ...Show more

Summary

The project chosen for the assignment is the house construction. This project required the completion of following activities that needed the duration specified according to the nature of tasks involved in each of them.
Foundation: This is the primary work in the whole process…
Author : mohammad09
The project chosen for the assignment is the house construction essay example
Read Text Preview
Save Your Time for More Important Things
Let us write or edit the assignment on your topic
"The project chosen for the assignment is the house construction"
with a personal 20% discount.
Grab the best paper

Related Essays

Project Management applied to House Renovation
This paper aims to discuss project management of house renovation which will be considered by senior management to effect measurable changes to an area in a home desired to be renovated. It specifically aimed to explicate a propose house renovation plan and explicate how performance management is significant for construction quality control and in the achievement of preferred outcomes.
14 pages (3500 words) Assignment
Project Management Assignment: Project Analysis
This report is based on the project analysis of the INCIS Fiasco, the idea of which was proposed by the New Zealand Police Force. The idea was to implement a compact Information System solution that would revolutionise the working mechanism of the police force.
10 pages (2500 words) Assignment
Construction Materials Assignment
The building is envisaged for reconstruction and this presents a number of options to designers such as timber frame, steel frame and composites. However, the final say on the matter can only be arrived at after balancing social, environmental and economic considerations for these differentiated methods of construction.
6 pages (1500 words) Assignment
Project Management for Construction Assignment
205. as per the directions of the commercial department, I have been in the process of undertaking an assessment of the project and its progress from all possible financial aspects and have made a number of observations with regards to the financial status of the project.
6 pages (1500 words) Assignment
HNC Construction Technology B Assignment
A high level of fittings and finishes are required. Various methods can be used for this, bearing in mind the following : build-ability, the suitability, and the health and safety. The construction of a seven storey service office in the inner city has its problems.
8 pages (2000 words) Assignment
Project Management for Construction
Stating clearly the additional information I still require. The report presented here gives a detailed analysis of the examination of a contract on construction offices and yards with regard to a company named Russ Ting Metal Stockholders plc. The report is based on the financial requirements specified by the Commercial Department of the Contractor and evaluates the financial status of the company considering the different factors that tend to determine the financial status of the project.
8 pages (2000 words) Assignment
Project Management Master Assignment
Project Management is a methodology and a discipline which can bring significant benefits to organizations. It ensures that limited resources are used on the right projects; manages complex changes in an organized way; assesses risks, defines goals and key success area and sets quality objectives.
6 pages (1500 words) Assignment
Church Construction Project
The criteria for selecting property are in its purposes. The church is a collection of people who are taught the Word of God by a priest or pastor. The church building is the temporal aspect of church. It is an asset which meets the requirement of a place to worship.
8 pages (2000 words) Assignment
Major factors in managing construction of house
3 pages (750 words) Assignment
Construction assignment
Relationship contract is the different styles of the contract that tries to achieve an outcome that can be accepted by all the parties involve. Partnering
2 pages (500 words) Assignment
Get a custom paper written
by a pro under your requirements!
Win a special DISCOUNT!
Put in your e-mail and click the button with your lucky finger
Your email
YOUR PRIZE:
Apply my DISCOUNT
Comments (0)
Rate this paper:
Thank you! Your comment has been sent and will be posted after moderation