The project chosen for the assignment is the house construction

Masters
Assignment
Miscellaneous
Pages 4 (1004 words)
Download 0
The project chosen for the assignment is the house construction. This project required the completion of following activities that needed the duration specified according to the nature of tasks involved in each of them.
Foundation: This is the primary work in the whole process…

Introduction

The time required is only 8 days. The time allocated was 10, which would be on a higher estimation. The major activity is only the fixing the roof components to the wall frames and placing the skylights. The necessary designs for the skylights could be prepared and fabricated early. Placing this could be undertaken along with the roof work. And the attaching the TV antenna shall also be undertaken along with this.
Plumbing and wiring: The plumbing and wiring could be simultaneously undertaken and requires 4 days each for this activity. As the it involves only fixing up of he components 6 days of plumbing could be reduced to 4 days as equivalent that of wiring.
Plastering: plastering work need to be undertaken after the plumbing and wiring, as any damages to the structure could be rectified at this stage. 4 days would be enough for this operation as it involves only covering the walls with appropriate mortar.
Foundation:, Frames: 14 December 2008, Roof: 22 December 2008, Skylight: 25 December 2008, TV antenna - 28 December 2008, Plumbing and wiring: 30 December 2008; Plastering: 3 January 2009; Finishing: 7 January 2009, Painting: 7 January 2009; Carpets, curtains and sides: 13 January 2009 and landscape: 15 January 2009.
The critical activities that would effect the shorted time required to complete the project are foundation, frames, roof, ...
Download paper
Not exactly what you need?

Related papers

The project chosen for the assignment is the house construction
The time required is only 8 days. The time allocated was 10, which would be on a higher estimation. The major activity is only the fixing the roof components to the wall frames and placing the skylights. The necessary designs for the skylights could be prepared and fabricated early. Placing this could be undertaken along with the roof work. And the attaching the TV antenna shall also be undertaken…
Construction Project Management
Secondly, in last two decades, the profession that comes up with growth and innovation. This profession has been fractured into many sub specialties. These include: real estate brokers, interior designers, municipal expediters, construction managers and on site inspection providers. I believe today's architect must be able to perform most of the above services in house or create a team to meet the…
Construction Economics Assignment
Many people took out very large mortgages. In 1983, the average new mortgage was approximately 2.1 times annual average earnings. By 1989 this had risen to 3.4 times annual average earnings.…
Church Construction Project
The selection of property to accommodate the church must commensurate the number of people in the church and the finance they are capable of raising to buy the church premises.…
Construction Project
The sector of construction has been playing some significance role in developed as well as undeveloped countries. The workforce in the developing countries such as Jordan is not perceived as a significant input to the industry despite the fact that labour from the construction project contribute the most significant and biggest percentage of the entire costs of project. Thus control of labour…
Villa Building and Construction
The bungalow will be of plinth area of 6800 sq ft, accommodating 4 bedrooms, two in the ground floor of 21.5 ft x 23 ft and 19.5 ft x 20 ft dimensions and two in the first floor of 21 ft x 23 ft and 19.5 x 20 ft dimensions, all with bath, closets attached, Great Room - Living, Dining and Kitchen of 30 ft x 40 ft , with two stone fire places, cherry cabinets and big screen HDTV,two wet bars with…
Major factors in managing construction of house
The completion of any project is the successful conglomeration of many factors. Construction of house is also no exception to this. The following factors must be taken care of by the project manager in the ensuring that all activities are completed in time.