5. A 3 day delay during test product step (K) will delay the project by 2 days. This is because K will be completed in 31 or 22 days; M will take 34 or 25 days from the K route; N will be completed in 36 or 27 days depending on route, and thus P will be completed in 37 or 28 days.


Hence, the minimum delay will be 2 days for completion of the project. However, since K is not on the critical path, the total project time will not be changed.
Network diagrams are used to provide a graphic and easy to read model of the activities required to complete the project. It provides the activities that are critical to manage the time duration of the project and identifies the activities that can be delayed without causing a delay in the overall project duration.