5. A 3 day delay during test product step (K) will delay the project by 2 days. This is because K will be completed in 31 or 22 days; M will take 34 or 25 days from the K route; N will be completed in 36 or 27 days depending on route, and thus P will be completed in 37 or 28 days…

Introduction

Hence, the minimum delay will be 2 days for completion of the project. However, since K is not on the critical path, the total project time will not be changed.
Network diagrams are used to provide a graphic and easy to read model of the activities required to complete the project. It provides the activities that are critical to manage the time duration of the project and identifies the activities that can be delayed without causing a delay in the overall project duration.
...
Download paper
Not exactly what you need?

Related papers

Assignment for the subject "Organizational Behavior". Writer MUST be ON TIME. Writer needs to send me some outlineideasANYTHING on the 10thMarch UK time 11am
It is not only the behaviour that is important in organisation, rather it is the elements that make up the behaviour that determine the extent to which people are working towards the organisational goals. This essay illuminates the impact of organisational culture on people's behaviour and elaborates how cultural environment affects performance.…
Emergency Assignment for the subject "Business Law". Writer MUST be ON TIME. Writer needs to send me some progresses on the 20thMarch UK time for tutor's permi
The treaty of Rome 1957 established the European atomic energy community (EURATOM). A second treaty of Rome 1957 established the European Economic Community (EEC), now contained in the treaty of European Union 1992, consolidated into the treaty of Amsterdam.…
Assignment for the subject "Managing Projects". Writer MUST be ON TIME. Writer needs to send me the task1 of the assignment on the 21stJune for me to go meeti
Hence, the minimum delay will be 2 days for completion of the project. However, since K is not on the critical path, the total project time will not be changed.…
Assignment for the subject "Value and Performance", of my course "Business Administration". Writer MUST be ON TIME. Writer needs to send me some progresses on t
This study focuses on the financial values of the company by carrying out a ratio analysis for the company and comparing the results with industry averages.…
Assignment for my course "International Accounting and Consultancy". Writer MUST be ON TIME. Writer needs to send me somethinganything on the 13thMarch UK tim
The IFRS make the entities achieve this purpose by enabling them to provide segment wise information. However the entities do not incur any excessive cost for such reporting; they are able to make only at a little extra cost. IFRS 8 arises from the IASB's comparison of International Accounting Standard 14 (IAS 14) 'Segment Reporting' with the US standard SFAS 131 'Disclosures about segments of an…