StudentShare
Contact Us
Sign In / Sign Up for FREE
Search
Go to advanced search...
Free

Contractual Advice for a Client - Essay Example

Cite this document
Summary
The essay "Contractual Advice for a Client" focuses on the critical analysis of the major issues in contractual advice for a client. This has reference to your query on whether a claim for an extension of time exists. Under the JCT contract, you have entered into…
Download full paper File format: .doc, available for editing
GRAB THE BEST PAPER93.3% of users find it useful
Contractual Advice for a Client
Read Text Preview

Extract of sample "Contractual Advice for a Client"

Contractual advice Dear Client, This has reference to your query on whether a claim for extension of time exists. Under the JCT contract you have entered into, if the contractor does not complete the work by the specified date of completion, then you must be paid the pre-agreed liquidated damages.1 But if it is delayed due to certain kinds of events he will be released from this obligation and an extension of time will be granted.2. Firstly, one of the reasons for seeking extension of time is the contention that the architect’s condemnation of the brickwork caused delays. From a legal standpoint, the architect is simply the administrator of the contract on behalf of the employer and may not modify or supplement the terms of the contract3, neither does he have the power to create new liabilities and obligations in the parties. Consequently, the architect is considered your employee and delays resulting from his/her side may be attributed to you rather than to the contractor. In this instance, since it is the architect who has required fresh obligations on the part of the contractor which may not have been a part of the original contract; therefore this particular extension of time of two days may have to be allowed. Further, this extension of time will also allow for financial recovery by the contractor. The contractor may be entitled to claim additional costs or loss and expense, because architect caused delays are the responsibility of the employer. I would thus conclude that the delay of time of 2 days caused by the architect requirements will have to be allowed and the contractor may also be entitled to loss and expense. Another cause of delay to the work on the ground floor is the freezing temperatures for three days. Under the JCT contract, it is only unusual or non typical weather conditions that can be grounds for extension of time. A contractor is expected to allow within the contract, some allowance for adverse weather conditions.4 Since the work was taken up in the months of January and February, where adverse weather conditions such as freezing temperatures have been known to occur, some provision should have been made by the contractor in the original contract. The weather records for the past five years or so must be compared to the weather patterns subsisting this year near this particular site and the contractor may be entitled to this extension only if the freezing temperatures are unusual or non typical, as compared to the weather records of previous years. I would also like to clarify that even if the extension is granted, “entitlement to an EOT does not automatically lead to entitlement to compensation and vice versa.”5 While it may be necessary to grant an extension of time, some causal factors of delay, i.e, for example, the adverse weather, will not allow the facility for financial recovery.6 Therefore, in this case, the contractor may not be eligible for loss and expense. In reference to the delays of 1 week caused by the Building Inspector’s disapproval of the installation of two piles, this extension may need to be allowed, but there may be some liability from the contractor. A contractor is required to comply with Building Regulations, therefore a failure to comply will be his liability. If the contractor has built in accordance with the contractual design but in contravention of building regulations, he will be liable whether or not he was aware that the design violated building regulations.7 On this basis, I conclude overall, that while the extension of time may have to be allowed, it does not appear that the contractor will be able to claim further loss and expense, except to the extent that delay has been caused by the architect’s requirements. You may be able to recover liquidated damages for the contractor’s delays, especially if you can show proven losses resulting from the failure to complete on time8. Since it is vital that the school is completed by August 1st, there may be a cause to demonstrate such losses. Under JCT 98, you can send a notification to the contractor of your intent to recover liquidated damages9, which could possibly function as a spur to get the current pending work completed sooner by making up for lost time. The architect may issue a certificate of non completion and even assuming the further extension of two weeks requested is granted, you can still give notification of your intent to recover liquidated damages and the agreed figure will then be recoverable even if you suffer no losses. Dear Contractor: This has reference to your query on the delays caused by the sub contractor’s insolvency. The subcontractor may be liable to the client as well as to you. The delay that may be caused by the sub contractor’s insolvency and the need to replace those services is especially relevant because of the possibility of liquidated damages being levied on you by the employer. Under contract law, the principles of negligence may be applicable, in accepting the contract without having the wherewithal to adequately complete the necessary responsibilities. Since the sub-contractors has entered into a contract you, he might have provided written warranties, which will be actionable under law and damages may be owed in negligence by the sub contractor10. The subcontractor may be liable for your damages11 because he has in effect, breached the contract. In considering the extent to which the sub contractor may have to fairly and reasonably compensate you for breach of the contract, factors to be taken into consideration may include “such as may be reasonably be supposed to have been in the contemplation of both parties at the time they made the contract, as the probable result of the breach of it.”12 At the time of making the contract, the sub contractor would have been aware if his financial situation was tenuous or falling far too short to successfully complete the requirements of the contract, therefore he would have been aware of the consequences of a possible breach and will be liable. Since you will also have to pay liquidated damages to the client, you are legally entitled to recover liquidated damages from the sub contractor only the extent that you are similarly penalized by the employer. In this instance, the delays and increase in price have been caused, but much will depend upon the manner in which the employer chooses to respond to the situation. If the employer allows you the necessary time to secure the services of another subcontractor and agrees to pay the extra amounts, then you may not have grounds to seek liquidated damages from the sub contractor.13 If you do not secure an extension, then it is also likely that the employer would withhold the retention monies to compensate for the damages/losses that are being sustained. In this case, you will also have the option to withhold the retention monies that are due to the sub contractor as well. Your sub contractor’s contract will generally allow you to retain half of the amounts due as retention monies, the release of which will be contingent upon the issue of a certificate that remedies any existing defects. In this instance, since the sub contractor is insolvent, he will be unable to issue the certificate because he cannot complete the construction as planned. The resultant damages may be compensated only through a retention by you, of the monies still owing to the sub contractor. Since the sub contractor, at the time of signing the contract was aware that monies would be retained until defects were made good, he may also not have much cause of action in disputing any such retention of monies. Dear Client, In respect to the warped flooring, the contractor and the designer may be held to be responsible for faulty construction and resultant damages. The designer/architect may be liable due to the reasonable standards of skill and care required of professionals like designers14 while the contractor may also be liable for the construction defects because he is responsible for the sub contractors’ workmanship and quality of materials supplied. The retention monies available in this case can be applied for the purpose for which they were designed, i.e, to function as protection in the event of contractor default. Since the construction of the ICT Room is still within the Defects Liability Period, this means that the monies need to be released only upon the issue of a Completion certificate after this period is completed satisfactorily, with no contractor defaults becoming apparent. In this case, as you have pointed out, the development of warping in the raised floor in the ICT room poses a danger to children. It is a direct result of a defect in construction, and the contractor will be liable for damages arising out of such warped floors, since they will be responsible under the law for negligent work15. In those cases where the Completion Certificate has not been issued, the retention monies will constitute an accruing debt and can be attached to redress any deficiencies that arise in the Defects Liability period after the completion of the contract. The retention monies are in effect, monies that are owed to the contractor in the future,; the extent to which they can be applied will depend on the circumstances of the case. Retention monies can be attached only on those cross claims which exist at the date of attachment and not those which may exist in the future16. Applying this in your case, the warping of the floor which presently exists can be attached, but not other possible defects which may arise as a result of the warped flooring in the future. I would also like to point out that such attachment of retention monies may not be possible in those cases where it is likely to cause injustice. In this instance, the designer/architect is also partly responsible for damages and the contractor cannot be held fully liable. Since the architect is considered to be the administrator of the employer, part of the liability may also rest upon you. As a result, the courts may not allow all the balance of retention monies to be attached, since this may result in an injustice to the contractor. However, some part of the retention monies can certainly be withheld from the contractor in view of the defects in construction, since he is now not eligible for the issue of the completion certificate. Bibliography * Barnes, Peter, 2006. “The JCT05 standard building sub-contract” Blackwell Publishing * Chappell, David, 2000. “Understanding JCT Standard Building Contracts”, Taylor and Francis at pp 80 * Kedah Kelang Papan Sdn Bhd v Hansol Sdn Bhd (1988) 1 ML 434 * Knocke, Jens, 1993. “Post construction liability and Insurance”, Taylor and Francis at pp 347 * Knowles, Roger, 2005. “150 contractual problems and their solutions”, Blackwell Publishing at pp 156 * Murdoch, John, 2000. “Construction contracts: Law and Management” Taylor and Francis at pp 280 * Patrington and Son v Tameside Metropolitan Borough Council(1985); cited in Chappell, David, 2002. “Parris’s Standard form of building contract: JCT 80” Blackwell Publishing * Powell-Smith, Vincent, Sims, John and Dancaster,Christopher,2000. “Contract documentation for Contractors” Blackwell Publishing at pp 145 Read More
Cite this document
  • APA
  • MLA
  • CHICAGO
(Contractual Advice Essay Example | Topics and Well Written Essays - 1750 words, n.d.)
Contractual Advice Essay Example | Topics and Well Written Essays - 1750 words. https://studentshare.org/business/1545629-contractual-advice
(Contractual Advice Essay Example | Topics and Well Written Essays - 1750 Words)
Contractual Advice Essay Example | Topics and Well Written Essays - 1750 Words. https://studentshare.org/business/1545629-contractual-advice.
“Contractual Advice Essay Example | Topics and Well Written Essays - 1750 Words”. https://studentshare.org/business/1545629-contractual-advice.
  • Cited: 0 times

CHECK THESE SAMPLES OF Contractual Advice for a Client

Analysis of Freds Situation in Law

In Rowley & Ors v Secretary of State for Department of Work and Pensions (2007) the Court held that 'a solicitor owes a duty of care in tort because, like any professional person, he or she voluntarily assumes responsibility towards an individual client', which applies to the case of Fred v.... Considering the fact that the question mentions Fred being surprised by the large bill from the Inland Revenue for capital gains tax, I suppose that he has listened to Paul's advice and sold some of his stocks and shares....
6 Pages (1500 words) Essay

Consequential and Pure Economic Loss in Negligence

When pure economic loss is negligently caused to a party to a contractual right or contract are made less valuable by the acts or omissions of a defendant, both instances that is where the terms of the contract have not been breached or violated, cannot give rise to a good cause of action and action to be taken.... However, these economic torts do not allow recovery of pure economic loss, as liability stems from the root of harm to some interest that can be protected in the hands of the claimant, such as harm to a business, procuring a breach of contractual rights, or some other actionable wrong....
6 Pages (1500 words) Essay

The Liability of Accountants and Auditors

owever, any lack of the proper degree of training, failure by the professional to attempt to follow up on a client's progress, failure to remain appropriately conversant with any new emerging discoveries in the field, or failure to refer to a specialist if it proves to be necessary can all be seen to constitute of negligence.... s exemplified in the line of reasoning followed in the Hedley Byrne ruling, when an adviser communicates information to an advisee so that the information might be used for a generally described or particularly specified purpose, and the advisee acts on this advice to his detriment, the adviser is found to fundamentally be guilty of negligence....
5 Pages (1250 words) Essay

The Effectiveness of Contractually Governed Partnering in the Construction Industry

Although contractual partnering is effective, especially for the client, it is not advisable to apply universal contract terms or strategies in their entirety to partnering arrangements.... "The Effectiveness of Contractually Governed Partnering in the Construction Industry" paper seeks to establish the effectiveness of contractually governed partnering arrangements in the UK construction sector....
57 Pages (14250 words) Dissertation

Role of Client Quantity Surveyor

This case study "Role of client Quantity Surveyor" discusses and compares the roles played by both client Quantity Surveyor and Contractor's quantity surveyor in detail and assesses the future developments within them.... Both client Quantity and Contractor's Quantity surveyor have similar knowledge and experience, but their roles differ depending on the one who has employed them.... The client's surveyor ensures that the client gets value for their money with a possibility of value increased asset with high-quality standards....
7 Pages (1750 words) Case Study

Administration of Construction Project Management

n cases where the contractor fails to comply by the recommended changes, the engineer is obliged to offer advice to the client.... Thus in this case, if the contractor fails to comply, I would advise the client to take the matter through a dispute resolution process using any possible method.... In most cases, the parties involved in the conflict might fail to effectively settle the matter, thus, as the engineer; I would advise the client to take the matter through litigation....
13 Pages (3250 words) Assignment

Contractual Remedies and Solutions in Case of Delay

The dispute at hand is in relation to the extension of time and the CA's position that does not acknowledge an issue in regard to the subject matter since they had furnished our client with the necessary information.... he contractor, who is our client presents to us a case of general delays and bad weather as the causes of the delay.... Preliminary reports from both the contract administrator and our client reveal that there is a need to conduct an investigation to determine the cause of the general delays....
10 Pages (2500 words) Assignment

Bankers Legal Duties

On opening an account with a bank, a banker has a contractual duty, under common law, never to disclose any client's information to any of the third parties.... his obligation also extends to any information received concerning the client, and every transaction and securities associated with the customers' accounts.... Bankers and customers have an existing contractual relationship.... For instance, in the case concerning Tournier v National Provincial Bank, the Court of Appeal agreed that the duty of confidentiality is contractual in nature, and was to be implied from the customer-banker relationship....
7 Pages (1750 words) Essay
sponsored ads
We use cookies to create the best experience for you. Keep on browsing if you are OK with that, or find out how to manage cookies.
Contact Us