An Analysis of the Woolcock Street Investments Case - Assignment Example

Only on StudentShare

Extract of sample
An Analysis of the Woolcock Street Investments Case

This case began in 1987 when the Eagle Star Nominees, Inc., designated as trustees for the BSL Growth Trust Company, engaged a company doing engineering work to design foundations for a warehouse and offices in Townsville. When the building’s construction had been finished, the trustee Eagle Star then decided to sell the property to the plaintiff. In the contract of sale, there was no warranty indicating that the building had no defects. Likewise, the buyer did not conduct any building inspection, survey before purchase, or any sort of appraisal to determine whether or not the building had been constructed in an optimal manner. Also, there was no assignment in contract by the vendor of the rights to proceed against others in case of defects.
Just more than a year after the property had been turned over, the defects become apparent. The building had unmistakable structural distress and this was because of how the foundations were arranged, as well as the material below the foundations. The buyer filed a case against the engineering company and its employee, stating that the company owed a duty of reasonable care in designing the foundations of the building and ensuring the safety of the premises. ...
Download paper

Summary

This essay begins by laying down the facts of the case at hand, it will then proceed with an analysis of the decision made by the High Court of Australia, the prior rulings (meaning, how did the courts decide in the older cases) and finally, providing a discussion on the important policy implications arising from the case…
Author : elfriedajast

Related Essays

Building a Catupult Research Paper
Range : The range is the distance covered by the ball after launch. The maximum range for parabolic path which the ball covers can be obtained at an angle of 45°. The horizontal distance from the point of launch to the point where the ball falls gives the range. 2. Trajectory : It is the path covered the ball, from the catapult after the launch the trajectory of the ball is parabolic. 3. Velocity : The rate of change of displacement is termed as the velocity. For a parabolic path the velocity of ball will be taken as the horizontal and vertical component of velocity at different points. 4.…
3 pages (753 words) Research Paper
Case Study Research Assignment
These alterations threaten to transform the global environment. As one author imagined it, “The year is 2035. In New York, palm trees line the Hudson River … Phoenix is in its third week of temperatures over 130 degrees … Holland is under water. Bangladesh has ceased to exist … in central Europe and in the American Midwest, decades of drought have turned once fertile agricultural lands into parched deserts (Rifkin, 1988).” Composition of Greenhouse Gases Methane and carbon dioxide primarily constitute the greenhouse gases. They also consist of water vapor and trace amounts of other…
6 pages (1506 words) Research Paper
CTV Building
The report produced by the Royal Commission had also officially identified the key players after the disaster. This report aims to evaluate the faults on the part of the key players and stakeholders leading to technical deficiencies in the design of the building. Gerald Shirtcliff was the CTV building’s site manager and he was later found to have faked his qualifications and therefore was not up to the mark. The head of the consultation firm, ARCL, Alan Reay was said to be “ultimately responsible” even though his designer and engineer David Harding was inexperienced in working with…
11 pages (2761 words) Assignment
The Canterbury Television (CTV) Building-Case Analysis
Most of the earthquakes witnessed in recent times have had devastating effects. Therefore, architects are advised to ensure that modern buildings meet the building standards capable of withstanding seismic waves of reasonably high magnitude. New Zealand is one of the European countries that have suffered from a series of earthquakes in the recent past. One such earthquake occurred on 22 February 2011 in Christchurch killing 184 individuals. Investigations conducted after the incident showed that the building collapsed due to poor design and construction. In addition, a number of players and…
6 pages (1506 words) Assignment
The Canterbury Television (CTV) Building Incident-Case Analysis
One such earthquake occurred on 22nd February 2011 in New Zealand causing 184 deaths with property worth billions of dollars being destroyed. This happened when an earthquake measuring 6.3 on the Richter scale hit Christchurch. The fact that only the Canterbury Television (CTV) Building collapsed following the earthquake have raised a lot of questions regarding the design and construction of the building. Investigations have since shown that the collapse occurred due to poor design and construction, several parties drawing blame for the collapse of the building. Several role players have been…
8 pages (2008 words) Assignment
Assignment: Engineering and Construction – The Case of CTV Building
The report also aims at formulating and organising the most important recommendations for the future course of action in the field of construction safety engineering. The analysis portion of the paper has been divided into to major subsections. In subsection 2.1, personnel management issues primarily with relation to the recruitment process of a building construction team have been analysed. Contextually, it should be mentioned that the credibility of the engineering team (that had constructed the CTV Building in late 1980s) is still under various questions. In subsection 2.2, modern disaster…
8 pages (2008 words) Assignment
CTV Building Collapse: Case Report
A number of investigations were carried out to figure out the causes of the building collapse and all the investigation reports pointed to poor building design and construction operations. The principal engineer Alan Reay employed an inexperienced engineer (David Harding) for the building design. In addition, Reay did not supervise the operations of Harding and hence many potential defects in the construction process had gone unidentified. To worsen the problem, the construction manager failed to properly guide the building’s foreman. The Christchurch City Council issued a permit for this…
8 pages (2008 words) Assignment
Got a tricky question? Receive an answer from students like you! Try us!