Construction Cost Control & Management Coursework example
Undergraduate
Coursework
Engineering and Construction
Pages 10 (2510 words)
Download 0
An approach list of the lodge substructure; The construction of the lodge will undergo three stages namely ground works, brick work, wall plastering and roofing. Each of the construction stages has several works and costs to be incurred in the process of the construction…

Introduction

The length of the lodge is 14 meters and the width is 10 meters. The rear roofing will not be excavated. The perimeter area that is to be excavated is the outer 2m width, and the depth will be 2.75 m. On the first day at the site, only the excavator and the driver will be present since the only work on that day will only involve digging up the ground. The material extracted is of poor quality and will be deposited in a pit far away from the site. The material is to be transported to a pit 8 km away by 20 tones capacity lorry. The number of lorries to be used during excavation period are two, which means the time taken to load one lorry is equal to the time taken by the other lorry to ferry the unwanted soil and come back. The time taken to load a lorry is estimated to be 30 minutes, thus, the speed of the lorry is 32 km per hour. That means in a day each lorry is expected to make 8 trips but one lorry will take one less trip which is lost at the start of the day meaning the total number made in a day are 15. Thus, the excavator and the general operations will take 12 days while the lorry and the loader will cover 12 days. The ground work will involve the laying down of a building foundation that will include parts of walls, piers and a column. ...
Download paper
Not exactly what you need?

Related papers

Development Appraisal, Project Cost Control
The building and construction sector includes contractors who build buildings for residential, industrial and commercial purposes. SECTION-A Question 1 This is a case whereby companies operating in the construction industry need to develop, differentiate, defend and communicate the development contribution they make to their host country  in just the same way as they manage the value they…
Construction Cost Control & Management
In our case, the formula is; (a + 4 m + p) / 6 (NetMBA, 2012). Where, O = Optimistic Time. M = most likely time. N = pessimistic time. Activity a days m days b days Expected Days a 4 m p (a + 4 m + p) / 6 AB 4 5 6 (4 + (4 *5) + 6) / 6 = 5 BC 2 5 8 (2 + (4 *5) + 8) / 6 = 5 CD 5 7 9 (5 + (4 *7) + 9) / 6 = 7 CE 4 5 6 (4 + (4 *5) + 6) / 6 = 5 DF 2 4 6 (2 + (4 *4) + 6) / 6 = 4 FG 3 5 9 (3 + (4 *5) + 9)…
Estimating and purchasing cost control
In this approach, the design package is reviewed and fully comprehended followed by the performance of a quantity survey of the scope of the project in question. In case little or no design and plan information is available, the Order-of-Magnitude Estimates approach is highly recommended. However, it is imperative that the contractor ensures he/she has all the requisite information to ensure…
Development Process in Construction Management
Hill & Jones (2009) explains a strategy to be a set or related actions that managers have to employ to increase the performance of their projects or companies. A strategy that would result to superior results as compared to the market practices would end up achieving a competitive advantage in the market, and such advantage would result to profitability, efficiency and effectiveness in the…
Estimating Purchasing and Cost Control
Cost management is an integral part of financial control and management in any for profit and non-profit organisation, notwithstanding the industry or sector. The same applies particularly to the engineering and construction sector in which the huge amounts of financial and other resources pumped must be accounted for to stakeholders such as the government, project funders and the…
Sustainable Construction, Management and Professional Studies
Moreover, there is also need to ensure that the repair works goes on well in accordance to the design. These expectations will actually be guided by the contracts between Uxbridge Water plc and the designer as well as the contractor for repair works. Consequently, this report outlines the procedure that will be used during the procurement and contract matters for the repair works. Procurement…
BIM and Construction management
The models created through BIM can be accessed by all concerned sides in the construction process for any adjustments or decision making in regard to how the construction work is to continue, how the building or facility will be used and if need be how demolition for the same will be done. It goes beyond the 2 dimensional representations of buildings on paper as plans, sections and elevations; and…