Project Scheduling

Masters
Essay
Miscellaneous
Pages 18 (4518 words)
Download 0
The uses of network analysis are as extensive as the subject itself. Planning, scheduling and control of large projects has become less difficult because of the tools of networking. Yet at the same time network analysis should not be seen as a tool for managing complexity in isolation…

Introduction

(Dilworth 1992, p.567)
Using the precedence diagram and activity schedule given, the following bar chart was made showing earliest and latest dates for activities A through K. To work out the early start and early finish of our network one has to start at the beginning activity, that is the activity/ activities with no predecessor. The early start of a job in a network is the earliest that a job can begin. In the case of a job with predecessors, the early start of a job is the largest of the early finish times of its predecessors. The early finish of a job is its early finish plus its own duration. This procedure of starting at the beginning and working out the early start and early finish of the activities in a network is often referred to as "forward pass".
without extending the total time of the project. Late finish of an activity is the late start of the activity that succeeds. If an activity has more than one successor, then the smaller of the late starts is to be taken. In the case of activities that do not have a successor, the late finish is taken as the total time of the project. The late start of such activities is their late finish less their duration.
Working out the late start of activities will help answer the questions: can the start of some activities be delayed, and if so by how much It must be mentioned at this juncture that this is a luxury that d ...
Download paper
Not exactly what you need?

Related papers

Project Management Bachelor Essay
It consists of five major systems as mentioned which can be briefly described as…
Techniques available for Resource allocation and aggregation in Construction Project Management
Resource management is more important in construction Management because common resources are utilized for different projects and it is essential that Project Scheduling be done keeping the resources availability into consideration. The project planning should be resource oriented scheduled.…
The importance of project plan
Planning a project involves the final project and all the support activities that assist in accomplishing the finished work. It also includes all the engineering, acquisition work and the management processes of the project. Any documentation and technical or non technical exchange of knowledge with the contractors also form part of the planning stage. Planning of any project also involves the…
The project management in the construction and operation of a restaurant
The technical component is necessary to recognize the critical activities that influence the total length of time a project takes to finish. The human resource elements deal with the issues of headship and worker inspiration within a group or team atmosphere.…
Project Scheduling
(Dilworth 1992, p.567)…
Scheduling and Implementation
It is almost like a unexplainable process for the choosing appropriate deadlines for appropriate tasks. It is like estimating the time based on some features and historical factors in correspondence with the task. When the exact deadlines are not given, this is the method that is chosen to estimate the deadline. If planning is done properly, the project scheduling can almost help in accurately…
Project Planning.
This project plan would help in optimally utilizing the available resources. Designing WBS in a proper fashion will help to understand the cost control techniques and the scheduling techniques that are needed to be adopted to ensure a smooth flow of operations in order to complete the project within the pre-determined time.…