Got a tricky question? Receive an answer from students like you! Try us!

Viual Aid and Gantt Chart - Essay Example

Author : joy20
Download 1

Summary

In recent year, many buinee have focued on three prioritie - cot, quality, and cycle time - in order to become world-cla companie (rikandarajah et al., 1998; Percy et al., 1997). It i trongly believed that thee three prioritie would make their buinee more competitive at the international market, thu, leading to improved profit generation…

Extract of sample
Viual Aid and Gantt Chart

For large organization, the focu i uually on improving the maintenance activitie uch that minimum amount of fund are expended (Anily et al., 1999; Alfare, 1999; Burke and mith, 1999a, b).
The high cot of breakdown maintenance could be unbearable uch that the need for preventive maintenance become obviou. The afety of equipment and employee i improved by preventive maintenance ervice. Thi ha ignificant impact on the production proce. Reaching maximum plant availability through minimal delay and breakdown and optimal equipment working condition reduce or eliminate the need for ubcontracting ome apect of the job (Chen and Liao, 2005; Cheung et al., 2005). Thi ha a reducing effect on the uually large maintenance budget of many organization. Maintenance cheduling i uually baed on preventive maintenance activitie (Oke, 2004). In an organization where a large number of equipment are operated, preventive maintenance cheduling offer a mean of achieving continuou indutrial operation without which ytem utenance would be extremely difficult. ince the cot of implementing preventive maintenance cheduling i more economical than that of replacing broken down equipment, in the long term, it i more economical to implement thi maintenance option.
ound maintenance cheduling i indipenable for high maintenance performance, which in turn facilitate the production pr ...
Download paper

Related Essays

Community College Financial Aid
Financial aid literally refers to "funding intended to help students pay tuition or other costs, such as room and board, for education at a college, university, or private school. General governmental funding for public education is not called financial aid, which refers to awards to specific individual students." (Wikipedia, 2006). The issue of financial aid - and community college financial aid in particular - is one which is subject to great interest and discussion. In order to come to a more understanding and intellectual viewpoint on this issue, the following questions must be answered:…
10 pages (2510 words)
Development Aid
Such countries began to borrow capital from other well to do rich countries to start developing their own economies and thus began the concept of Development Aid. There has been a lot of monetary transfer between the poor countries and the developed countries with regard to the development aid. Development Aid was made mandatory by the United Nations in the year 1946 to ensure that the countries which were destroyed and affected adversely during the World-War II, to recover from their state. The concept of providing Development Aid was to help the third world countries recover from their…
7 pages (1757 words)
Activity with Viual Aid
I, too, waѕ impreѕѕed when I previewed Baѕecamp'ѕ featureѕ in Ѕoftware Development'ѕ People and Projectѕ Newѕletter in May 2004. However, aѕ I've grown more familiar with Baѕecamp, I've found it hard to overlook one important detail: The application haѕ no way to produce a Gantt chart. Gantt chartѕ—thoѕe horizontal bar chartѕ that ѕhow dependencieѕ between taѕkѕ and the eѕtimated time in which they might be completed—have been the mainѕtay of project managerѕ ever ѕince mechanical engineer Henry Gantt demonѕtrated in the early 1900ѕ how one can be uѕed to track…
5 pages (1255 words)
Data Warehouse Gantt Chart and PERT Chart
The task assignments have overloaded certain resources. This is because, when setting predecessors, only adjacent tasks have been considered in certain cases. For example, some of the tasks to which the resource named Goran has been allocated on the same day are 75, 76, 109 and 110. Task 76 has a dependency on task 75 and task 110 has a dependency on task 109. But, because the same resource is involved, there is a dependency between tasks 76 and 109 as well. Ignoring dependencies such as these has resulted in that resource been overloaded. Hence tasks assignments need to be reworked.…
2 pages (502 words)
Log book/diary and Gantt chart.
Then I will enter its details in the log book to determine the project overall progress.…
4 pages (1004 words)
Pareto chart
4. What should you do in terms of staffing for that particular month? More staffs should be hired to carter for this temporary demand of staff. Also the management should come up with a work schedule so that staffs work for more hours and get extra payment for those hours. The management should be ready in terms of providing all necessary material required for the usage at this time. Motivation allowances for the workers should also be considered to make them have the morale to
1 pages (251 words)